Grids package: Council and Parliament agree to streamline permitting for a faster clean energy transition
Today, the Council and the European Parliament reached a provisional agreement to accelerate permit-granting procedures for renewable energy projects, electricity grids and storage facilities. The objective is to boost their deployment across the European Union, reinforce the EU’s energy security and make our energy network fit for climate neutrality.
The permitting directive is half of the European grids package, which seeks to modernise and expand Europe’s energy infrastructure. The European grids package is a key deliverable under the ‘One Europe, One Market’ roadmap aimed at boosting competitiveness and lowering energy prices.
The permitting directive amends the renewable energy directive, the electricity market directive, and the gas market directive.
“With tonight’s provisional agreement on the permitting directive, we have completed the first half of the European grids package. We are delivering on the ambition in the ‘One Europe, One Market’ roadmap.
Faster, streamlined permitting will help accelerate electrification in Europe. We need grid infrastructure for clean, affordable, and homegrown energy and to break our dependence on imported fossil fuels. Successfully concluding the permitting directive follows months of interinstitutional negotiations, and this agreement represents one of the most significant legislative milestones in the EU’s energy agenda. I am proud of Ireland’s role in concluding this cornerstone file during our presidency.”
– Darragh O’Brien, Ireland’s Minister for Climate, Energy and the Environment
Simplified and shortened permitting
The co-legislators agreed to make permit-granting procedures faster and more transparent, eliminating unnecessary delays and streamlining deadlines for the approval and grid connection of renewable energy projects, energy storage facilities and recharging stations and for the authorisation of new electricity and gas infrastructure.
Member states will be able to prioritise the roll-out of renewable energy and electricity grids by presuming them to be of overriding public interest. The provisional agreement aligns with the Council’s position, leaving to member states the discretion not to apply this principle in order to protect security and defence and cultural heritage interests.
Cutting delays through tacit approval
To prevent administrative bottlenecks, member states may decide that a lack of response from authorities for intermediary administrative steps of permit-granting is deemed to be tacit approval, as outlined in the Council’s position.
Digitalising permit applications
The provisional agreement provides for the establishment of single digital portals or connected portals at the appropriate administrative level for permitting procedures. The portals will make permit applications faster and simpler through an efficient and transparent procedure, providing a single point of access for applicants.
Public acceptance and community participation
The co-legislators agreed to foster public support and facilitate a smooth transition to a cleaner energy system. The agreement establishes principles for citizen engagement in renewables projects: these include promoting dialogue through the voluntary designation of an independent facilitator and fair benefit-sharing with local communities hosting renewable energy projects with an installed capacity above 7 MW.
Next steps
The provisional agreement will now have to be endorsed by the Council and the Parliament. It will then be formally adopted by both institutions following legal-linguistic revision. Member states will have 1.5 years to incorporate the provisions of the directive into their national legislation.
Background
According to the Draghi report on EU competitiveness and the action plan for affordable energy, lengthy and complex permitting processes are significantly slowing down the expansion of electricity grids needed for clean energy and lower energy costs in the EU. Currently, electricity transmission grids take around 10 years to complete, with permitting accounting for more than half of that timeframe.
The permitting directive was proposed by the European Commission in December 2025, to address bottlenecks in the permitting procedures for renewable energy projects and energy infrastructure such as electricity and gas grids, storage and recharging stations, in order to accelerate electrification and decarbonisation.